Greenspark starts 200 kWp installation

Early December 2018 our installation team started with the second phase of what will become a 500 kWp solar system for several warehouses.

In August 2018 the first phase of 300 kWp was commissioned. The system is performing very well. 

As per February 2019, the 500 kWp system will be operational and is expected to produce 730 MWh per year and save the customer over US$ 120,000 annually.